Dayton WRF Final Clarifiers
Project Description:
Peterson Construction Company was low bidder in June 2016 and was awarded a contract in September 2016. Construction started in December 2016 and achieved substantial completion by December 2017 which was approximately seven (7) months ahead of schedule. Scope of the project included replacement of eight (8) 160’ Final Clarifier mechanisms. Also included was RAS Pump and piping work in the basement of the existing sludge pump building and new Sodium Hypochlorite Storage Tanks and Feed Equipment.
Construction Cost: $9.5 million
Year Completed: 2018